| Assessment Year | 1996 |
|---|---|
| Principal Product | Corn and Flour Tortillas |
| NAICS |
n/a
|
| SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
| Sales Range | $5 M to 10M |
| # of Employees | 106 |
| Plant Area |
30,000
ft2
|
| Annual Production | 285,000,000
pieces
|
| Production Hrs. Annual | 5,590
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $86,200 | 961,899 |
kWh
|
$0.090 |
| Electricity Demand | $21,265 | 2,660 |
kW-mo/yr
|
$7.99 |
| Electricity Fees | $6,426 | - |
|
- |
| Natural Gas | $88,190 | 13,459 |
MMBtu
|
$6.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,505 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,505 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $1,474 | $3,186 |
$1,025
16,999
kWh
|
$385
-
kW-mo/yr
|
$64 | - | - | |
| 02 | 2.4235: Remove or close off unneeded compressed air lines | $4,305 | $500 |
$4,080
67,116
kWh
|
- | $225 | - | - | |
| 03 | 2.7135: Install occupancy sensors | $105 | $144 |
$105
1,758
kWh
|
- | - | - | - | |
| 04 | 2.2511: Insulate bare equipment | $1,116 | $211 |
$1,116
49,824
kWh
|
- | - | - | - | |
| 05 | 3.5311: Recover and reuse waste material | $258 | - | - | - | - | - |
$258
-
lb
|
|
| 06 | 3.4151: Minimize water usage | $247 | $900 | - | - | - |
$247
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $7,505 | $4,941 |
$6,326
135,697
kWh
|
$385
-
kW-mo/yr
|
$289 |
$247
-
Tgal
|
$258
-
lb
|
||
| TOTAL IMPLEMENTED | $7,505 | $4,941 |
$6,326
135,697
kWh
|
$385
-
kW-mo/yr
|
$289 |
$247
-
Tgal
|
$258
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs