ITAC Assessment: NV0044
ITAC logo
ITAC Assessment: NV0044
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Multi-Part Business Forms
NAICS
n/a
SIC 2761: Manifold Business Forms
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 45,000
ft2
Annual Production 44,400,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $124,422 1,907,679
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,757 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,310

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7111: Reduce illumination to minimum necessary levels $2,702 $175 $2,702
31,653
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,457 $978 $5,457
85,580
kWh
03 2.7135: Install occupancy sensors $1,544 $736 $1,544
33,705
kWh
04 2.1131: Repair faulty insulation in furnaces, boilers, etc $903 $911 $903
19,637
kWh
05 2.4133: Use most efficient type of electric motors $2,151 $4,335 $2,151
43,669
kWh
TOTAL RECOMMENDED $12,757 $7,135 $12,757
214,244
kWh
TOTAL IMPLEMENTED $10,310 $5,488 $10,310
160,902
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs