ITAC Assessment: NV0040
ITAC logo
ITAC Assessment: NV0040
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Rolled, Sheet, and Tube Steel Products
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $5
M
to 10
M
# of Employees 65
Plant Area 71,600
ft2
Annual Production 2,500
ton
Production Hrs. Annual 2,730
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $83,060 714,244
kWh
Natural Gas $10,506 1,619
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,053 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,566

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $1,149 $709 $1,149
8,206
kWh
02 2.7145: Install skylights $6,192 $20,963 $6,192
44,549
kWh
03 2.7135: Install occupancy sensors $295 $164 $295
2,052
kWh
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $417 $100 $417
2,931
kWh
TOTAL RECOMMENDED $8,053 $21,936 $8,053
57,738
kWh
TOTAL IMPLEMENTED $1,566 $809 $1,566
11,137
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs