ITAC Assessment: NV0038
ITAC logo
ITAC Assessment: NV0038
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Bare Printed Circuit Boards
NAICS
n/a
SIC 3672: Printed Circuit Boards
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area 40,000
ft2
Annual Production 170
thousand feet
Production Hrs. Annual 4,420
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $141,324 1,628,664
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,238 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,558

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7145: Install skylights $1,238 $7,568 $1,238
12,603
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,751 $530 $1,751
24,326
kWh
03 2.7135: Install occupancy sensors $557 $491 $557
6,448
kWh
04 2.4133: Use most efficient type of electric motors $356 $46 $356
4,396
kWh
05 2.1131: Repair faulty insulation in furnaces, boilers, etc $191 $84 $191
3,224
kWh
06 2.4231: Reduce the pressure of compressed air to the minimum required $260 - $260
4,103
kWh
07 2.2511: Insulate bare equipment $885 $189 $885
10,258
kWh
TOTAL RECOMMENDED $5,238 $8,908 $5,238
65,358
kWh
TOTAL IMPLEMENTED $2,558 $660 $2,558
36,049
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs