ITAC Assessment: NV0017
ITAC logo
ITAC Assessment: NV0017
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Wood Mouldings
NAICS
n/a
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 130,000
ft2
Annual Production 6,000,000
units
Production Hrs. Annual 2,990
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $134,113 1,405,334
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,328 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,617

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $6,998 - $6,998
74,736
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,930 $888 $1,930
20,223
kWh
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,689 $200 $1,689
17,585
kWh
04 2.7421: Reduce glazed areas in buildings $151 $653 $151
1,465
kWh
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $10,560 - $10,560
-
kWh
TOTAL RECOMMENDED $21,328 $1,741 $21,328
114,009
kWh
TOTAL IMPLEMENTED $10,617 $1,088 $10,617
112,544
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs