| Assessment Year | 1994 |
|---|---|
| Principal Product | Aerosol Paints, Lubricants, and Cleaners. |
| NAICS |
n/a
|
| SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
150,000
ft2
|
| Annual Production | 11,000,000
pieces
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Nevada |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $125,200 | 1,449,297 |
kWh
|
$0.086 |
| Natural Gas | $64,207 | 11,505 |
MMBtu
|
$5.58 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,074 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,436 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $4,613 | $724 |
$4,613
58,324
kWh
|
- | |
| 02 | 2.7243: Improve air circulation with destratification fans / other methods | $5,710 | $1,540 | - |
$5,710
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,503 | $1,059 |
$1,503
18,464
kWh
|
- | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $181 | - |
$181
2,345
kWh
|
- | |
| 05 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $105 | $56 | - |
$105
-
MMBtu
|
|
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $597 | $100 |
$597
7,620
kWh
|
- | |
| 07 | 2.2511: Insulate bare equipment | $139 | $172 | - |
$139
-
MMBtu
|
|
| 08 | 2.2437: Recover waste heat from equipment | $2,226 | $900 | - |
$2,226
-
MMBtu
|
|
| TOTAL RECOMMENDED | $15,074 | $4,551 |
$6,894
86,753
kWh
|
$8,180
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $7,436 | $1,724 |
$5,210
65,944
kWh
|
$2,226
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs