| Assessment Year | 2026 |
|---|---|
| Principal Product | Fracking Pumps |
| NAICS | 333912: Air and Gas Compressor Manufacturing |
| SIC | 3561: Pumps and Pumping Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
90,000
ft2
|
| Annual Production | 720
units
|
| Production Hrs. Annual | 3,298
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $106,971 | 2,560,334 |
kWh
|
$0.042 | |
| Electricity Demand | $277,886 | 29,275 |
kW-mo/yr
|
$9.49 | |
| Electricity Fees | $14,130 | - |
|
- | |
| Natural Gas | $30,501 | 2,549 |
MMBtu
|
$11.97 | |
| Waste Disposal Costs | |||||
| Water Usage | $7,115 | 12,876 |
Tgal
|
$0.55 | |
| TOTAL YEARLY COSTS | $436,603 | ||||
| RECOMMENDED SAVINGS* | $353,383 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4321: Upgrade obsolete equipment | $214,633 | $1,203,000 |
$855
20,470
kWh
|
$778
-
kW-mo/yr
|
- | - | $63,000 | $150,000 | |
| 02 | 2.7232: Replace existing hvac unit with high efficiency model | $83,537 | $362,950 |
$3,152
75,431
kWh
|
- | - | - | - | $80,385 | |
| 03 | 2.8121: Apply for tax-free status for energy purchases | $32,870 | $5,000 | - | - | $32,870 | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,162 | $35,316 |
$5,529
132,340
kWh
|
$4,633
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.6218: Turn off equipment when not in use | $8,377 | $625 | - | - | - |
$8,377
-
MMBtu
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,483 | $5,753 |
$1,359
32,538
kWh
|
$1,124
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,320 | - |
$723
17,302
kWh
|
$597
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $353,383 | $1,612,644 |
$11,618
278,081
kWh
|
$7,132
-
kW-mo/yr
|
$32,870 |
$8,377
-
MMBtu
|
$63,000 | $230,385 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs