Assessment Year | 2025 |
---|---|
Principal Product | Coated Linerboard |
NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2671: Packaging Paper and Plastics Film, Coated and Laminated |
Sales Range | $10 M to 50M |
# of Employees | 43 |
Plant Area |
40,000
ft2
|
Annual Production | 33,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $73,043 | 2,196,186 |
kWh
|
$0.033 | |
Electricity Demand | $43,101 | 5,699 |
kW-mo/yr
|
$7.56 | |
Electricity Fees | $3,901 | - |
|
- | |
Natural Gas | $20,778 | 5,667 |
MMBtu
|
$3.67 | |
Waste Disposal Costs | |||||
Water Usage | $75,072 | 16,616 |
Tgal
|
$4.52 | |
TOTAL YEARLY COSTS | $215,895 | ||||
RECOMMENDED SAVINGS* | $163,620 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,238 | - |
$862
25,877
kWh
|
$376
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,568 | $5,609 |
$1,788
53,679
kWh
|
$780
-
kW-mo/yr
|
- | - | |
03 | 4.431: Train operators for maximum operating efficiency | $150,000 | $12,000 | - | - | - | $150,000 | |
04 | 2.3212: Optimize plant power factor | $6,649 | $5,965 | - | - | $6,649 | - | |
05 | 4.812: Apply for investment incentives | $3,165 | $5,000 | - | - | $3,165 | - | |
TOTAL RECOMMENDED | $163,620 | $28,573 |
$2,649
79,555
kWh
|
$1,157
-
kW-mo/yr
|
$9,814 | $150,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs