Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Trucks
NAICS 423110: Automobile and Other Motor Vehicle Merchant Wholesalers
SIC 5511: Motor Vehicle Dealers (New and Used)
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 178,000
ft2
Annual Production 13,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,929 974,900
kWh
Electricity Demand $25,828 2,682
kW-mo/yr
Natural Gas $106,730 124,928
MMBtu
Waste Disposal Costs
Water Usage $19,764 1,447
Tgal
TOTAL YEARLY COSTS $249,251
RECOMMENDED SAVINGS* $202,614 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $4,136 - $3,487
35,080
kWh
$649
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,914 $5,609 $2,456
24,709
kWh
$458
-
kW-mo/yr
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,511 $906 $5,489
55,216
kWh
$1,023
-
kW-mo/yr
- -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $36,410 $21,995 - - $36,410 -
05 2.3212: Optimize plant power factor $2,643 $1,302 - $2,643
-
kW-mo/yr
- -
06 4.632: Change operating conditions $150,000 $1,200,000 - - - $150,000
TOTAL RECOMMENDED $202,614 $1,229,812 $11,431
115,005
kWh
$4,772
-
kW-mo/yr
$36,410 $150,000
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs