Assessment Year | 2024 |
---|---|
Principal Product | Trucks |
NAICS | 423110: Automobile and Other Motor Vehicle Merchant Wholesalers |
SIC | 5511: Motor Vehicle Dealers (New and Used) |
Sales Range | $10 M to 50M |
# of Employees | 135 |
Plant Area |
178,000
ft2
|
Annual Production | 13,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $96,929 | 974,900 |
kWh
|
$0.099 | |
Electricity Demand | $25,828 | 2,682 |
kW-mo/yr
|
$9.63 | |
Natural Gas | $106,730 | 124,928 |
MMBtu
|
$0.85 | |
Waste Disposal Costs | |||||
Water Usage | $19,764 | 1,447 |
Tgal
|
$13.66 | |
TOTAL YEARLY COSTS | $249,251 | ||||
RECOMMENDED SAVINGS* | $202,614 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,136 | - |
$3,487
35,080
kWh
|
$649
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,914 | $5,609 |
$2,456
24,709
kWh
|
$458
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,511 | $906 |
$5,489
55,216
kWh
|
$1,023
-
kW-mo/yr
|
- | - | |
04 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $36,410 | $21,995 | - | - | $36,410 | - | |
05 | 2.3212: Optimize plant power factor | $2,643 | $1,302 | - |
$2,643
-
kW-mo/yr
|
- | - | |
06 | 4.632: Change operating conditions | $150,000 | $1,200,000 | - | - | - | $150,000 | |
TOTAL RECOMMENDED | $202,614 | $1,229,812 |
$11,431
115,005
kWh
|
$4,772
-
kW-mo/yr
|
$36,410 | $150,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs