Assessment Year | 2023 |
---|---|
Principal Product | helicopter blades |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 180 |
Plant Area |
160,000
ft2
|
Annual Production | 1,200
pieces
|
Production Hrs. Annual | 5,356
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $516,683 | 6,060,235 |
kWh
|
$0.085 | |
Electricity Demand | $266,665 | 13,536 |
kW-mo/yr
|
$19.70 | |
Electricity Fees | $45,795 | - |
|
- | |
Natural Gas | $242,913 | 23,419 |
MMBtu
|
$10.37 | |
Waste Disposal Costs | |||||
Water Usage | $15,182 | 2,097 |
Tgal
|
$7.24 | |
TOTAL YEARLY COSTS | $1,087,238 | ||||
RECOMMENDED SAVINGS* | $258,309 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $80,204 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,491 | $4,553 |
$6,254
73,322
kWh
|
$3,236
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $18,251 | - |
$12,027
141,001
kWh
|
$6,223
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $33,277 | $33,920 |
$21,930
257,088
kWh
|
$11,347
-
kW-mo/yr
|
- | - | |
04 | 2.2511: Insulate bare equipment | $3,147 | $11,909 | - | - |
$3,147
-
MMBtu
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $27,816 | $16,551 |
$18,331
214,905
kWh
|
$9,485
-
kW-mo/yr
|
- | - | |
06 | 4.812: Apply for investment incentives | $52,462 | - | - | - | - | $52,462 | |
07 | 2.7232: Replace existing hvac unit with high efficiency model | $113,865 | $96,040 |
$9,137
107,120
kWh
|
$4,728
-
kW-mo/yr
|
- | $100,000 | |
TOTAL RECOMMENDED | $258,309 | $162,973 |
$67,680
793,436
kWh
|
$35,020
-
kW-mo/yr
|
$3,147
-
MMBtu
|
$152,462 | ||
TOTAL IMPLEMENTED | $80,204 | $4,553 |
$18,282
214,323
kWh
|
$9,460
-
kW-mo/yr
|
- | $52,462 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs