| Assessment Year | 2023 |
|---|---|
| Principal Product | Electrical component manufacturing |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 44 |
| Plant Area |
41,304
ft2
|
| Annual Production | 294,193
units
|
| Production Hrs. Annual | 6,912
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $61,314 | 686,960 |
kWh
|
$0.089 | |
| Electricity Demand | $27,112 | 5,672 |
kW-mo/yr
|
$4.78 | |
| Electricity Fees | $7,991 | - |
|
- | |
| Natural Gas | $9,392 | 931 |
MMBtu
|
$10.09 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,400 | 89 |
Tgal
|
$27.00 | |
| TOTAL YEARLY COSTS | $108,209 | ||||
| RECOMMENDED SAVINGS* | $60,653 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,307 | $5,753 |
$2,111
23,635
kWh
|
$196
-
kW-mo/yr
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,261 | - |
$12,133
135,866
kWh
|
$1,128
-
kW-mo/yr
|
- | |
| 03 | 2.3212: Optimize plant power factor | $4,823 | $5,241 | - |
$4,823
-
kW-mo/yr
|
- | |
| 04 | 3.1191: Change procedures / equipment / operating conditions | $37,440 | $111,000 | - | - | $37,440 | |
| 05 | 2.7425: Clean or color roof to reduce solar load | $1,400 | $1,600 |
$1,080
12,094
kWh
|
$320
-
kW-mo/yr
|
- | |
| 06 | 2.7221: Lower temperature during the winter season and vice-versa | $1,423 | - |
$1,423
15,930
kWh
|
- | - | |
| TOTAL RECOMMENDED | $60,653 | $123,594 |
$16,746
187,525
kWh
|
$6,467
-
kW-mo/yr
|
$37,440 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs