| Assessment Year | 2023 |
|---|---|
| Principal Product | Railroad Rolling Stock Manufacturing |
| NAICS | 336510: Railroad Rolling Stock Manufacturing |
| SIC | 3743: Railroad Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 400 |
| Plant Area |
1,000,000
ft2
|
| Annual Production | 294
pieces
|
| Production Hrs. Annual | 4,032
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,307,419 | 13,979,212 |
kWh
|
$0.094 | |
| Electricity Demand | $347,419 | 38,438 |
kW-mo/yr
|
$9.04 | |
| Electricity Fees | $158,276 | - |
|
- | |
| Natural Gas | $222,765 | 20,997 |
MMBtu
|
$10.61 | |
| Waste Disposal Costs | |||||
| Water Usage | $105,394 | 4,253 |
Tgal
|
$24.78 | |
| TOTAL YEARLY COSTS | $2,141,273 | ||||
| RECOMMENDED SAVINGS* | $150,675 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,687 | $5,993 |
$6,754
71,846
kWh
|
$1,933
-
kW-mo/yr
|
|
| 02 | 2.7425: Clean or color roof to reduce solar load | $38,000 | $38,000 |
$26,600
282,878
kWh
|
$11,400
-
kW-mo/yr
|
|
| 03 | 2.7124: Make a practice of turning off lights when not needed | $29,874 | - |
$23,999
255,312
kWh
|
$5,875
-
kW-mo/yr
|
|
| 04 | 2.3212: Optimize plant power factor | $27,237 | $63,579 | - |
$27,237
-
kW-mo/yr
|
|
| 05 | 2.7221: Lower temperature during the winter season and vice-versa | $735 | - |
$735
7,816
kWh
|
- | |
| 06 | 2.7221: Lower temperature during the winter season and vice-versa | $27,449 | - |
$27,449
292,431
kWh
|
- | |
| 07 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $18,694 | - |
$17,803
189,389
kWh
|
$892
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $150,675 | $107,572 |
$103,338
1,099,671
kWh
|
$47,337
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs