ITAC Assessment: NT0003
ITAC logo
ITAC Assessment: NT0003
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Bread
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $5
M
to 10
M
# of Employees 63
Plant Area 85,000
ft2
Annual Production 20,000,000
pieces
Production Hrs. Annual 4,780
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $162,605 2,277,457
kWh
Electricity Demand $63,894 6,387
kW-mo/yr
Electricity Fees $753 -
Natural Gas $87,057 7,931
MMBtu
Waste Disposal Costs
Water Usage $17,862 2,031
Tgal
TOTAL YEARLY COSTS $332,171
RECOMMENDED SAVINGS* $54,699 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,267 $5,705 $2,417
33,857
kWh
$850
-
kW-mo/yr
02 2.3212: Optimize plant power factor $12,262 $21,725 - $12,262
-
kW-mo/yr
03 2.7142: Utilize higher efficiency lamps and/or ballasts $10,623 $24,707 $8,675
121,507
kWh
$1,947
-
kW-mo/yr
04 2.7135: Install occupancy sensors $3,289 $1,600 $3,289
46,055
kWh
-
05 2.2533: Replace air curtain doors with solid doors $2,238 $3,193 $2,238
31,347
kWh
-
06 2.7232: Replace existing hvac unit with high efficiency model $23,020 $185,220 $23,020
322,456
kWh
-
TOTAL RECOMMENDED $54,699 $242,150 $39,639
555,222
kWh
$15,059
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs