| Assessment Year | 2023 |
|---|---|
| Principal Product | Bread |
| NAICS | 311812: Commercial Bakeries |
| SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
| Sales Range | $5 M to 10M |
| # of Employees | 63 |
| Plant Area |
85,000
ft2
|
| Annual Production | 20,000,000
pieces
|
| Production Hrs. Annual | 4,780
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $162,605 | 2,277,457 |
kWh
|
$0.071 | |
| Electricity Demand | $63,894 | 6,387 |
kW-mo/yr
|
$10.00 | |
| Electricity Fees | $753 | - |
|
- | |
| Natural Gas | $87,057 | 7,931 |
MMBtu
|
$10.98 | |
| Waste Disposal Costs | |||||
| Water Usage | $17,862 | 2,031 |
Tgal
|
$8.79 | |
| TOTAL YEARLY COSTS | $332,171 | ||||
| RECOMMENDED SAVINGS* | $54,699 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,267 | $5,705 |
$2,417
33,857
kWh
|
$850
-
kW-mo/yr
|
|
| 02 | 2.3212: Optimize plant power factor | $12,262 | $21,725 | - |
$12,262
-
kW-mo/yr
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,623 | $24,707 |
$8,675
121,507
kWh
|
$1,947
-
kW-mo/yr
|
|
| 04 | 2.7135: Install occupancy sensors | $3,289 | $1,600 |
$3,289
46,055
kWh
|
- | |
| 05 | 2.2533: Replace air curtain doors with solid doors | $2,238 | $3,193 |
$2,238
31,347
kWh
|
- | |
| 06 | 2.7232: Replace existing hvac unit with high efficiency model | $23,020 | $185,220 |
$23,020
322,456
kWh
|
- | |
| TOTAL RECOMMENDED | $54,699 | $242,150 |
$39,639
555,222
kWh
|
$15,059
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs