| Assessment Year | 2026 |
|---|---|
| Principal Product | Pet Health and Wellness |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $100 M to 500M |
| # of Employees | 200 |
| Plant Area |
490,000
ft2
|
| Annual Production | 25,000,000
units
|
| Production Hrs. Annual | 4,240
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $218,527 | 3,507,072 |
kWh
|
$0.062 | |
| Electricity Demand | $91,983 | 10,909 |
kW-mo/yr
|
$8.43 | |
| Electricity Fees | $26,096 | - |
|
- | |
| Natural Gas | $22,876 | 2,457 |
MMBtu
|
$9.31 | |
| Fuel Oil #2 | $37,573 | 1,546 |
MMBtu
|
$24.30 | |
| Waste Disposal Costs | |||||
| Water Usage | $7,525 | 2,374 |
Tgal
|
$3.17 | |
| Water Disposal | $13,095 | 2,374 |
Tgal
|
$5.52 | |
| Other Liquid (non-haz) | $4,658 | 1 |
gal
|
$4,658.00 | |
| TOTAL YEARLY COSTS | $422,333 | ||||
| RECOMMENDED SAVINGS* | $1,131,206 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Water Disposal Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.114: Add/modify equipment to improve drying process | $1,000,000 | $4,000,000 | - | - | - |
$34,638
-
MMBtu
|
- | - | $965,362 | |
| 02 | 4.112: Replace old machine with new automatic multi-station tool | $60,812 | $449,510 |
$1,953
31,500
kWh
|
$759
-
kW-mo/yr
|
- | - | - | $58,100 | - | |
| 03 | 2.7243: Improve air circulation with destratification fans / other methods | $41,053 | $15,088 | - | - |
$317
-
MMBtu
|
- | - | $41,828 | $(-1,092.0) | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,667 | $35,427 |
$10,909
175,945
kWh
|
$4,948
-
kW-mo/yr
|
- | - | - | $811 | - | |
| 05 | 2.7135: Install occupancy sensors | $4,260 | $6,131 |
$4,260
68,706
kWh
|
- | - | - | - | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,667 | $413 |
$3,667
59,144
kWh
|
- | - | - | - | - | - | |
| 07 | 2.4239: Eliminate or reduce compressed air usage | $2,434 | $12,996 |
$2,434
39,258
kWh
|
- | - | - | - | - | - | |
| 08 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,348 | $800 | - | - | - | - |
$3,748
-
Tgal
|
$(-2,400.0) | - | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $965 | $3,202 |
$1,715
27,668
kWh
|
- | - | - | - | $(-750.0) | - | |
| TOTAL RECOMMENDED | $1,131,206 | $4,523,567 |
$24,938
402,221
kWh
|
$5,707
-
kW-mo/yr
|
$317
-
MMBtu
|
$34,638
-
MMBtu
|
$3,748
-
Tgal
|
$97,589 | $964,270 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Water Disposal Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs