| Assessment Year | 2026 |
|---|---|
| Principal Product | Paper and Cardboard |
| NAICS | 322130: Paperboard Mills |
| SIC | 2631: Paperboard Mills |
| Sales Range | $100 M to 500M |
| # of Employees | 175 |
| Plant Area |
332,000
ft2
|
| Annual Production | 260,000
ton
|
| Production Hrs. Annual | 8,472
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $6,995,231 | 113,589,492 |
kWh
|
$0.062 | |
| Electricity Demand | $1,267,097 | 176,764 |
kW-mo/yr
|
$7.17 | |
| Electricity Fees | $418,954 | - |
|
- | |
| Natural Gas | $441,081 | 44,219 |
MMBtu
|
$9.97 | |
| Paper | $356,933 | 1 |
MMBtu
|
$356,933.00 | |
| Other Gas | $30,296 | 1 |
MMBtu
|
$30,296.00 | |
| Other Energy | $7,115,077 | 908,599 |
MMBtu
|
$7.83 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,654 | 802 |
Tgal
|
$3.31 | |
| Water Disposal | $7,136 | 802 |
Tgal
|
$8.90 | |
| Other Liquid (non-haz) | $595 | 1 |
gal
|
$595.00 | |
| Other Liquid (haz) | $761,750 | 194,252 |
gal
|
$3.92 | |
| Solid Waste (non-haz) | $51,834 | 1 |
lb
|
$51,834.00 | |
| TOTAL YEARLY COSTS | $17,448,638 | ||||
| RECOMMENDED SAVINGS* | $54,607 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $25,200 | $106,628 | - | - | - | - | $25,200 | |
| 02 | 2.7135: Install occupancy sensors | $22,579 | $12,180 |
$22,579
364,173
kWh
|
- | - | - | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,798 | $348 |
$2,404
38,779
kWh
|
$394
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,068 | $7,582 |
$957
15,432
kWh
|
$382
-
kW-mo/yr
|
- | $729 | - | |
| 05 | 3.4155: Meter waste water | $1,962 | $2,300 | - | - |
$1,962
-
Tgal
|
- | - | |
| TOTAL RECOMMENDED | $54,607 | $129,038 |
$25,940
418,384
kWh
|
$776
-
kW-mo/yr
|
$1,962
-
Tgal
|
$729 | $25,200 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs