ITAC Assessment: NL0118
ITAC logo
ITAC Assessment: NL0118
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Popcorn Products
NAICS 311919: Other Snack Food Manufacturing
SIC 2096: Potato Chips, Corn Chips, and Similar Snacks
Sales Range $50
M
to 100
M
# of Employees 113
Plant Area 185,000
ft2
Annual Production 18,000,000
lb
Production Hrs. Annual 5,880
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $114,361 3,970,770
kWh
Electricity Demand $198,863 9,043
kW-mo/yr
Electricity Fees $29,527 -
Natural Gas $210,684 35,220
MMBtu
Other Gas $10,319 1
MMBtu
Waste Disposal Costs
Water Usage $22,120 6,605
Tgal
Water Disposal $22,137 6,605
Tgal
Other Liquid (non-haz) $98,371 1
gal
TOTAL YEARLY COSTS $706,382
RECOMMENDED SAVINGS* $20,920 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings
01 2.3132: Recharge batteries on during off-peak demand periods $15,441 $550 - $15,441
-
kW-mo/yr
-
02 3.4155: Meter waste water $3,352 $1,575 - - $3,352
-
Tgal
03 3.4155: Meter waste water $857 $985 - - $857
-
Tgal
04 2.4231: Reduce the pressure of compressed air to the minimum required $636 $165 $636
21,932
kWh
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $634 $608 $310
10,693
kWh
$324
-
kW-mo/yr
-
TOTAL RECOMMENDED $20,920 $3,883 $946
32,625
kWh
$15,765
-
kW-mo/yr
$4,209
-
Tgal
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs