Assessment Year | 2025 |
---|---|
Principal Product | Wood Pellets & Animal Bedding |
NAICS | 321999: All Other Miscellaneous Wood Product Manufacturing |
SIC | 2499: Wood Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 16 |
Plant Area |
45,774
ft2
|
Annual Production | 450,000
units
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $158,862 | 3,227,600 |
kWh
|
$0.049 | |
Electricity Demand | $157,312 | 11,537 |
kW-mo/yr
|
$13.64 | |
Electricity Fees | $335 | - |
|
- | |
Natural Gas | $12,265 | 1,363 |
MMBtu
|
$9.00 | |
Waste Disposal Costs | |||||
Water Usage | $735 | 29 |
Tgal
|
$25.34 | |
Water Disposal | $664 | 29 |
Tgal
|
$22.90 | |
Other Liquid (non-haz) | $292 | 1 |
gal
|
$292.00 | |
TOTAL YEARLY COSTS | $330,465 | ||||
RECOMMENDED SAVINGS* | $213,651 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.642: Install sensors to detect and avoid jams | $200,000 | $80,000 | - | - | - | - | - | $200,000 | |
02 | 2.4235: Remove or close off unneeded compressed air lines | $5,808 | $510 |
$5,808
118,537
kWh
|
- | - | - | - | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,060 | $90 | - |
$3,060
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,459 | $45 |
$1,439
29,370
kWh
|
- | $(-180.0) | $(-100.0) | $1,300 | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,055 | $515 |
$605
12,359
kWh
|
$450
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.6226: Optimize filtration cleaning / replacement to minimize air resistance | $748 | $2,330 |
$748
15,272
kWh
|
- | - | - | - | - | |
07 | 2.4322: Use or replace with energy efficient substitutes | $521 | $191 |
$521
10,623
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $213,651 | $83,681 |
$9,121
186,161
kWh
|
$3,510
-
kW-mo/yr
|
$(-180.0) | $(-100.0) | $1,300 | $200,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs