ITAC Assessment: NL0112
ITAC logo
ITAC Assessment: NL0112
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Patient Care
NAICS 622110: General Medical and Surgical Hospitals
SIC 8062: General Medical and Surgical Hospitals
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 37,520
ft2
Annual Production 12,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,143 1,152,316
kWh
Electricity Demand $32,072 2,342
kW-mo/yr
Natural Gas $15,627 1,866
MMBtu
Other Gas $106 1
MMBtu
Waste Disposal Costs
Water Usage $1,809 562
Tgal
Water Disposal $1,745 562
Tgal
Other Liquid (non-haz) $2,795 1
gal
TOTAL YEARLY COSTS $117,297
RECOMMENDED SAVINGS* $1,188 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $440 $783 $270
4,916
kWh
$170
-
kW-mo/yr
- -
02 2.7241: Install outside air damper / economizer on hvac unit $379 $1,435 $379
6,892
kWh
- - -
03 2.7135: Install occupancy sensors $219 $248 $173
3,137
kWh
- $25 $21
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $112 $547 $83
1,518
kWh
$29
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $38 $58 $23
418
kWh
$15
-
kW-mo/yr
- -
TOTAL RECOMMENDED $1,188 $3,071 $928
16,881
kWh
$214
-
kW-mo/yr
$25 $21
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs