ITAC Assessment: NL0110
ITAC logo
ITAC Assessment: NL0110
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Corrugated Boxes
NAICS 322211: Corrugated and Solid Fiber Box Manufacturing
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $50
M
to 100
M
# of Employees 120
Plant Area 330,000
ft2
Annual Production 667,000
thousand feet
Production Hrs. Annual 6,600
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $336,509 5,563,008
kWh
Electricity Demand $105,425 15,049
kW-mo/yr
Electricity Fees $26,554 -
Natural Gas $298,208 43,088
MMBtu
Waste Disposal Costs
Water Usage $19,424 4,288
Tgal
Water Disposal $11,313 2,160
Tgal
Other Liquid (non-haz) $2,305 1
gal
Solid Waste (non-haz) $21,631 2,000
lb
TOTAL YEARLY COSTS $821,369
RECOMMENDED SAVINGS* $280,256 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.9114: Use solar heat to make electricty $262,812 $4,671,994 $220,752
3,679,200
kWh
$42,060
-
kW-mo/yr
- - -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $7,360 $160 - $7,840
-
kW-mo/yr
- $(-480.0) -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,063 $4,500 $5,803
96,718
kWh
- - $(-640.0) $(-100.0)
04 3.4155: Meter waste water $4,494 $2,400 - - $4,494
-
Tgal
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $527 $700 $435
7,251
kWh
$92
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $280,256 $4,679,754 $226,990
3,783,169
kWh
$49,992
-
kW-mo/yr
$4,494
-
Tgal
$(-1,120.0) $(-100.0)
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs