| Assessment Year | 2025 |
|---|---|
| Principal Product | Corrugated Boxes |
| NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $50 M to 100M |
| # of Employees | 120 |
| Plant Area |
330,000
ft2
|
| Annual Production | 667,000
thousand feet
|
| Production Hrs. Annual | 6,600
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $336,509 | 5,563,008 |
kWh
|
$0.060 | |
| Electricity Demand | $105,425 | 15,049 |
kW-mo/yr
|
$7.01 | |
| Electricity Fees | $26,554 | - |
|
- | |
| Natural Gas | $298,208 | 43,088 |
MMBtu
|
$6.92 | |
| Waste Disposal Costs | |||||
| Water Usage | $19,424 | 4,288 |
Tgal
|
$4.53 | |
| Water Disposal | $11,313 | 2,160 |
Tgal
|
$5.24 | |
| Other Liquid (non-haz) | $2,305 | 1 |
gal
|
$2,305.00 | |
| Solid Waste (non-haz) | $21,631 | 2,000 |
lb
|
$10.82 | |
| TOTAL YEARLY COSTS | $821,369 | ||||
| RECOMMENDED SAVINGS* | $280,256 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $262,812 | $4,671,994 |
$220,752
3,679,200
kWh
|
$42,060
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,360 | $160 | - |
$7,840
-
kW-mo/yr
|
- | $(-480.0) | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,063 | $4,500 |
$5,803
96,718
kWh
|
- | - | $(-640.0) | $(-100.0) | |
| 04 | 3.4155: Meter waste water | $4,494 | $2,400 | - | - |
$4,494
-
Tgal
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $527 | $700 |
$435
7,251
kWh
|
$92
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $280,256 | $4,679,754 |
$226,990
3,783,169
kWh
|
$49,992
-
kW-mo/yr
|
$4,494
-
Tgal
|
$(-1,120.0) | $(-100.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs