ITAC Assessment: AS0255
ITAC logo
ITAC Assessment: AS0255
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Jet Engine Components
NAICS
n/a
SIC 3724: Aircraft Engines and Engine Parts
Sales Range $10
M
to 50
M
# of Employees 310
Plant Area 100,000
ft2
Annual Production 22,800
pieces
Production Hrs. Annual 4,800
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $264,284 4,718,347
kWh
Electricity Demand $33,183 11,521
kW-mo/yr
Electricity Fees $22,782 -
Natural Gas $52,021 8,070
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,633 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $10,341 $20,474 $6,588
171,454
kWh
$3,753
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $358 $442 $171
4,396
kWh
$48
-
kW-mo/yr
- $65 - $74
03 2.6211: Conserve energy by efficient use of vending machines $1,365 $195 $1,064
26,964
kWh
$301
-
kW-mo/yr
- - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $2,392 $120 $1,100
27,843
kWh
$1,292
-
kW-mo/yr
- - - -
05 2.7232: Replace existing hvac unit with high efficiency model $10,137 $14,500 $6,513
164,127
kWh
$3,624
-
kW-mo/yr
- - - -
06 3.6192: Use a less expensive method of waste removal $5,779 $120 - - $5,779
-
gal
- - -
07 4.821: Pay bills on time to avoid late fees $3,261 $60 - - - - $3,261 -
08 4.513: Re-arrange equipment layout to reduce labor costs $12,000 $1,500 - - - $12,000 - -
TOTAL RECOMMENDED $45,633 $37,411 $15,436
394,784
kWh
$9,018
-
kW-mo/yr
$5,779
-
gal
$12,065 $3,261 $74
TOTAL IMPLEMENTED $12,000 $1,500 - - - $12,000 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs