Assessment Year | 1999 |
---|---|
Principal Product | Jet Engine Components |
NAICS |
n/a
|
SIC | 3724: Aircraft Engines and Engine Parts |
Sales Range | $10 M to 50M |
# of Employees | 310 |
Plant Area |
100,000
ft2
|
Annual Production | 22,800
pieces
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $264,284 | 4,718,347 |
kWh
|
$0.056 |
Electricity Demand | $33,183 | 11,521 |
kW-mo/yr
|
$2.88 |
Electricity Fees | $22,782 | - |
|
- |
Natural Gas | $52,021 | 8,070 |
MMBtu
|
$6.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,633 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,341 | $20,474 |
$6,588
171,454
kWh
|
$3,753
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $358 | $442 |
$171
4,396
kWh
|
$48
-
kW-mo/yr
|
- | $65 | - | $74 | |
03 | 2.6211: Conserve energy by efficient use of vending machines | $1,365 | $195 |
$1,064
26,964
kWh
|
$301
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,392 | $120 |
$1,100
27,843
kWh
|
$1,292
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $10,137 | $14,500 |
$6,513
164,127
kWh
|
$3,624
-
kW-mo/yr
|
- | - | - | - | |
06 | 3.6192: Use a less expensive method of waste removal | $5,779 | $120 | - | - |
$5,779
-
gal
|
- | - | - | |
07 | 4.821: Pay bills on time to avoid late fees | $3,261 | $60 | - | - | - | - | $3,261 | - | |
08 | 4.513: Re-arrange equipment layout to reduce labor costs | $12,000 | $1,500 | - | - | - | $12,000 | - | - | |
TOTAL RECOMMENDED | $45,633 | $37,411 |
$15,436
394,784
kWh
|
$9,018
-
kW-mo/yr
|
$5,779
-
gal
|
$12,065 | $3,261 | $74 | ||
TOTAL IMPLEMENTED | $12,000 | $1,500 | - | - | - | $12,000 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs