ITAC Assessment: NL0101
ITAC logo
ITAC Assessment: NL0101
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Recycled Rubber Products
NAICS 326291: Rubber Product Manufacturing for Mechanical Use
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 88
Plant Area 55,562
ft2
Annual Production 40,000,000
lb
Production Hrs. Annual 8,568
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $450,450 7,678,500
kWh
Electricity Demand $90,508 16,283
kW-mo/yr
Electricity Fees $64,419 -
Natural Gas $3,409 1,955
MMBtu
Waste Disposal Costs
Water Usage $15,236 3,158
Tgal
Water Disposal $27,793 3,158
Tgal
Other Liquid (non-haz) $58,721 1
gal
Solid Waste (non-haz) $4,320 180,000
lb
TOTAL YEARLY COSTS $714,856
RECOMMENDED SAVINGS* $45,276 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Usage Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $28,125 $8,785 - - $28,125 - - - - - - -
02 3.4111: Use closed cycle process to minimize waste water production $8,730 $7,424 - - - $5,419
-
Tgal
$9,886
-
Tgal
$3,392
-
gal
- $(-9,968.0) - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,849 $7,210 $2,225
37,924
kWh
$625
-
kW-mo/yr
- - - - - - - -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $2,520 $1,700 - - - - - - $4,320
-
lb
- - $(-1,800.0)
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,117 $315 $2,117
36,087
kWh
- - - - - - - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $670 $175 $1,050
17,908
kWh
- - - - - - $(-280.0) $(-100.0) -
07 2.7135: Install occupancy sensors $265 $1,404 $265
4,515
kWh
- - - - - - - - -
TOTAL RECOMMENDED $45,276 $27,013 $5,657
96,434
kWh
$625
-
kW-mo/yr
$28,125 $5,419
-
Tgal
$9,886
-
Tgal
$3,392
-
gal
$4,320
-
lb
$(-10,248.0) $(-100.0) $(-1,800.0)
TOTAL IMPLEMENTED - - - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Usage Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs