Assessment Year | 2024 |
---|---|
Principal Product | Ready to Eat Desserts |
NAICS | 311412: Frozen Specialty Food Manufacturing |
SIC | 2024: Ice Cream and Frozen Desserts |
Sales Range | $100 M to 500M |
# of Employees | 175 |
Plant Area |
226,687
ft2
|
Annual Production | 79,122
ton
|
Production Hrs. Annual | 8,664
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,440,846 | 37,489,299 |
kWh
|
$0.038 | |
Electricity Demand | $1,473,685 | 64,082 |
kW-mo/yr
|
$23.00 | |
Electricity Fees | $24,482 | - |
|
- | |
Natural Gas | $761,074 | 196,442 |
MMBtu
|
$3.87 | |
Fuel Oil #1 | $540,000 | 18,725 |
MMBtu
|
$28.84 | |
Waste Disposal Costs | |||||
Water Usage | $488,528 | 146,048 |
Tgal
|
$3.34 | |
Water Disposal | $491,718 | 146,048 |
Tgal
|
$3.37 | |
Other Liquid (non-haz) | $40,407 | 146,048 |
gal
|
$0.28 | |
TOTAL YEARLY COSTS | $5,260,740 | ||||
RECOMMENDED SAVINGS* | $4,674,476 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #1 Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2622: Replace existing chiller with high efficiency model | $3,986,937 | $49,000,000 |
$247,324
6,508,485
kWh
|
- |
$540,000
-
MMBtu
|
$3,199,613 | |
02 | 2.3212: Optimize plant power factor | $569,646 | $74,000 | - | - | - | $569,646 | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $102,668 | $214,595 | - |
$102,668
-
MMBtu
|
- | - | |
04 | 2.2425: Use flue gases to heat process or service water | $8,784 | $35,100 | - |
$8,784
-
MMBtu
|
- | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $6,201 | $140 |
$6,201
163,160
kWh
|
- | - | - | |
06 | 2.8114: Change rate schedules or other changes in utility service | $240 | $35 | - | - | - | $240 | |
TOTAL RECOMMENDED | $4,674,476 | $49,323,870 |
$253,525
6,671,645
kWh
|
$111,452
-
MMBtu
|
$540,000
-
MMBtu
|
$3,769,499 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #1 Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs