Assessment Year | 2024 |
---|---|
Principal Product | Patient Care |
NAICS | 622110: General Medical and Surgical Hospitals |
SIC | 8062: General Medical and Surgical Hospitals |
Sales Range | $10 M to 50M |
# of Employees | 260 |
Plant Area |
150,000
ft2
|
Annual Production | 20,075
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $192,658 | 2,840,985 |
kWh
|
$0.068 | |
Electricity Demand | $137,853 | 7,746 |
kW-mo/yr
|
$17.80 | |
Natural Gas | $95,345 | 11,276 |
MMBtu
|
$8.46 | |
Waste Disposal Costs | |||||
Water Usage | $19,573 | 307,719 |
Tgal
|
$0.064 | |
Water Disposal | $16,347 | 291,785 |
Tgal
|
$0.056 | |
TOTAL YEARLY COSTS | $461,776 | ||||
RECOMMENDED SAVINGS* | $12,297 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1224: Replace boiler | $6,690 | $32,200 |
$(-11,885.0)
(-174,795)
kWh
|
$19,575
-
MMBtu
|
- | $(-1,000.0) | |
02 | 2.7245: Use direct air supply to exhaust hoods | $4,787 | $10,040 |
$4,787
70,401
kWh
|
- | - | - | |
03 | 3.5311: Recover and reuse waste material | $820 | $6,490 | - | - | $217 | $603 | |
TOTAL RECOMMENDED | $12,297 | $48,730 |
$(-7,098.0)
(-104,394)
kWh
|
$19,575
-
MMBtu
|
$217 | $(-397.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs