ITAC Assessment: NL0096
ITAC logo
ITAC Assessment: NL0096
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Metal Food Cans
NAICS 332431: Metal Can Manufacturing
SIC 3411: Metal Cans
Sales Range $100
M
to 500
M
# of Employees 120
Plant Area 143,000
ft2
Annual Production 432,000,000
units
Production Hrs. Annual 8,400
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $628,660 8,978,800
kWh
Electricity Demand $213,415 17,812
kW-mo/yr
Electricity Fees $185,102 -
Natural Gas $425,801 60,618
MMBtu
Waste Disposal Costs
Water Usage $5,494 1,214
Tgal
Water Disposal $892 1,214
Tgal
Other Liquid (non-haz) $3,961 1,214
gal
TOTAL YEARLY COSTS $1,463,325
RECOMMENDED SAVINGS* $240,251 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
01 2.4239: Eliminate or reduce compressed air usage $58,179 $20,000 $44,561
636,587
kWh
$13,618
-
kW-mo/yr
- - - - -
02 2.7243: Improve air circulation with destratification fans / other methods $45,060 $54,620 $8,484
121,296
kWh
$2,076
-
kW-mo/yr
- - - - $34,500
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $40,407 $21,500 $42,427
606,100
kWh
- - $(-1,920.0) $(-100.0) - -
04 2.8121: Apply for tax-free status for energy purchases $37,143 $3,000 - - - - - $37,143 -
05 2.3132: Recharge batteries on during off-peak demand periods $20,701 $600 - $20,701
-
kW-mo/yr
- - - - -
06 2.4221: Install compressor air intakes in coolest locations $15,679 $4,600 $15,679
223,990
kWh
- - - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $12,185 $29,089 $8,744
124,857
kWh
$2,133
-
kW-mo/yr
- $1,308 - - -
08 2.2414: Use waste heat from hot flue gases to preheat $5,899 $11,800 - - $5,899
-
MMBtu
- - - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,634 $1,540 $4,634
66,182
kWh
- - - - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $364 $172 $111
1,576
kWh
$26
-
kW-mo/yr
- $227 - - -
TOTAL RECOMMENDED $240,251 $146,921 $124,640
1,780,588
kWh
$38,554
-
kW-mo/yr
$5,899
-
MMBtu
$(-385.0) $(-100.0) $37,143 $34,500
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs