| Assessment Year | 2024 |
|---|---|
| Principal Product | Metal Food Cans |
| NAICS | 332431: Metal Can Manufacturing |
| SIC | 3411: Metal Cans |
| Sales Range | $100 M to 500M |
| # of Employees | 120 |
| Plant Area |
143,000
ft2
|
| Annual Production | 432,000,000
units
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $628,660 | 8,978,800 |
kWh
|
$0.070 | |
| Electricity Demand | $213,415 | 17,812 |
kW-mo/yr
|
$11.98 | |
| Electricity Fees | $185,102 | - |
|
- | |
| Natural Gas | $425,801 | 60,618 |
MMBtu
|
$7.02 | |
| Waste Disposal Costs | |||||
| Water Usage | $5,494 | 1,214 |
Tgal
|
$4.53 | |
| Water Disposal | $892 | 1,214 |
Tgal
|
$0.73 | |
| Other Liquid (non-haz) | $3,961 | 1,214 |
gal
|
$3.26 | |
| TOTAL YEARLY COSTS | $1,463,325 | ||||
| RECOMMENDED SAVINGS* | $240,251 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $152,912 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $58,179 | $80,000 |
$44,561
636,587
kWh
|
$13,618
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.7243: Improve air circulation with destratification fans / other methods | $45,060 | $54,620 |
$8,484
121,296
kWh
|
$2,076
-
kW-mo/yr
|
- | - | - | - | $34,500 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $40,407 | $21,500 |
$42,427
606,100
kWh
|
- | - | $(-1,920.0) | $(-100.0) | - | - | |
| 04 | 2.8121: Apply for tax-free status for energy purchases | $37,143 | $3,000 | - | - | - | - | - | $37,143 | - | |
| 05 | 2.3132: Recharge batteries on during off-peak demand periods | $20,701 | $600 | - |
$20,701
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $15,679 | $4,600 |
$15,679
223,990
kWh
|
- | - | - | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,185 | $29,089 |
$8,744
124,857
kWh
|
$2,133
-
kW-mo/yr
|
- | $1,308 | - | - | - | |
| 08 | 2.2414: Use waste heat from hot flue gases to preheat | $5,899 | $11,800 | - | - |
$5,899
-
MMBtu
|
- | - | - | - | |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,634 | $1,540 |
$4,634
66,182
kWh
|
- | - | - | - | - | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $364 | $172 |
$111
1,576
kWh
|
$26
-
kW-mo/yr
|
- | $227 | - | - | - | |
| TOTAL RECOMMENDED | $240,251 | $206,921 |
$124,640
1,780,588
kWh
|
$38,554
-
kW-mo/yr
|
$5,899
-
MMBtu
|
$(-385.0) | $(-100.0) | $37,143 | $34,500 | ||
| TOTAL IMPLEMENTED | $152,912 | $135,301 |
$100,477
1,435,302
kWh
|
$15,777
-
kW-mo/yr
|
- | $(-385.0) | $(-100.0) | $37,143 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs