| Assessment Year | 2024 |
|---|---|
| Principal Product | Vehicle Cabins |
| NAICS | 333120: Construction Machinery Manufacturing |
| SIC | 3531: Construction Machinery and Equipment |
| Sales Range | $100 M to 500M |
| # of Employees | 190 |
| Plant Area |
230,000
ft2
|
| Annual Production | 6,000
units
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $76,782 | 1,004,800 |
kWh
|
$0.076 | |
| Electricity Demand | $33,365 | 2,704 |
kW-mo/yr
|
$12.34 | |
| Electricity Fees | $30,131 | - |
|
- | |
| Natural Gas | $28,225 | 3,227 |
MMBtu
|
$8.75 | |
| Other Gas | $6,064 | 1 |
MMBtu
|
$6,064.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $17,850 | 10,278 |
Tgal
|
$1.74 | |
| TOTAL YEARLY COSTS | $192,417 | ||||
| RECOMMENDED SAVINGS* | $93,613 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $1,285 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $65,447 | $72,000 |
$970
12,756
kWh
|
$427
-
kW-mo/yr
|
- | - | - | $64,050 | |
| 02 | 2.3132: Recharge batteries on during off-peak demand periods | $14,437 | $500 | - |
$14,437
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.8121: Apply for tax-free status for energy purchases | $11,145 | $2,000 | - | - | - | - | $11,145 | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,285 | $1,500 |
$2,185
28,750
kWh
|
- | $(-800.0) | $(-100.0) | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $652 | $373 |
$365
4,803
kWh
|
$139
-
kW-mo/yr
|
$148 | - | - | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $647 | $2,000 |
$647
8,509
kWh
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $93,613 | $78,373 |
$4,167
54,818
kWh
|
$15,003
-
kW-mo/yr
|
$(-652.0) | $(-100.0) | $11,145 | $64,050 | ||
| TOTAL IMPLEMENTED | $1,285 | $1,500 |
$2,185
28,750
kWh
|
- | $(-800.0) | $(-100.0) | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs