ITAC Assessment: NL0086
ITAC logo
ITAC Assessment: NL0086
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Beef products
NAICS 311611: Animal (except Poultry) Slaughtering
SIC 2011: Meat Packing Plants
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 125,263
ft2
Annual Production 79,289,558
lb
Production Hrs. Annual 2,250
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $805,885 14,714,010
kWh
Electricity Demand $338,686 26,716
kW-mo/yr
Electricity Fees $82,151 -
Natural Gas $128,414 11,851
MMBtu
Waste Disposal Costs
Water Usage $44,340 30,408
Tgal
Water Disposal $65,529 30,408
Tgal
TOTAL YEARLY COSTS $1,465,005
RECOMMENDED SAVINGS* $59,500 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,441

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings
01 2.2621: Modify refrigeration system to operate at a lower pressure $48,136 $100,000 $36,959
674,431
kWh
$11,177
-
kW-mo/yr
- -
02 2.2511: Insulate bare equipment $6,202 $6,211 $4,709
85,938
kWh
$1,492
-
kW-mo/yr
- -
03 3.4155: Meter waste water $4,239 $1,348 - - $4,239
-
Tgal
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $573 $510 $435
7,940
kWh
$138
-
kW-mo/yr
- -
05 2.6125: Keep equipment clean $350 $450 - - - $350
TOTAL RECOMMENDED $59,500 $108,519 $42,103
768,309
kWh
$12,807
-
kW-mo/yr
$4,239
-
Tgal
$350
TOTAL IMPLEMENTED $10,441 $7,559 $4,709
85,938
kWh
$1,492
-
kW-mo/yr
$4,239
-
Tgal
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs