Assessment Year | 2006 |
---|---|
Principal Product | Automotive Exterior Parts |
NAICS | 325211: Plastics Material and Resin Manufacturing |
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $100 M to 500M |
# of Employees | 650 |
Plant Area |
310,000
ft2
|
Annual Production | 1,200,000
pieces
|
Production Hrs. Annual | 7,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,185,270 | 46,559,211 |
kWh
|
$0.047 |
Electricity Demand | $261,920 | 73,097 |
kW-mo/yr
|
$3.58 |
Electricity Fees | $173,850 | - |
|
- |
Natural Gas | $1,903,922 | 159,982 |
MMBtu
|
$11.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,100,621 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $35,604 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $870,069 | $100,000 | - |
$870,069
-
MMBtu
|
- | - | |
02 | 3.1161: Eliminate/reduce an operation | $137,445 | - | - |
$137,445
-
MMBtu
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,153 | - |
$9,153
167,637
kWh
|
- | - | - | |
04 | 2.4226: Use / purchase optimum sized compressor | $9,806 | $18,000 |
$9,806
179,600
kWh
|
- | - | - | |
05 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $29,400 | - | - | - |
$29,400
-
lb
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,653 | $550 |
$1,653
30,275
kWh
|
- | - | - | |
07 | 4.821: Pay bills on time to avoid late fees | $6,204 | - | - | - | - | $6,204 | |
08 | 2.4239: Eliminate or reduce compressed air usage | $36,891 | $62,250 |
$36,891
675,659
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $1,100,621 | $180,800 |
$57,503
1,053,171
kWh
|
$1,007,514
-
MMBtu
|
$29,400
-
lb
|
$6,204 | ||
TOTAL IMPLEMENTED | $35,604 | - | - | - |
$29,400
-
lb
|
$6,204 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs