ITAC Assessment: NL0083
ITAC logo
ITAC Assessment: NL0083
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Treated Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $500
k
to 1
M
# of Employees 2
Plant Area 24,488
ft2
Annual Production 210,240
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,096 1,232,240
kWh
Electricity Demand $36,312 2,598
kW-mo/yr
Electricity Fees $999 -
Natural Gas $5,078 604
MMBtu
Waste Disposal Costs
Water Usage $1 1
Tgal
TOTAL YEARLY COSTS $105,486
RECOMMENDED SAVINGS* $70,463 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $58,625

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 3.4155: Meter waste water $31,255 $151,280 $1,255
24,515
kWh
- - $30,000
02 2.4323: Use optimum size and capacity equipment $18,134 $8,660 $11,376
222,189
kWh
$6,758
-
kW-mo/yr
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $11,038 $4,600 $1,066
20,652
kWh
$(-28.0)
-
kW-mo/yr
- $10,000
04 2.4133: Use most efficient type of electric motors $8,182 $4,945 $8,182
160,151
kWh
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $854 $2,700 $588
11,484
kWh
$266
-
kW-mo/yr
- -
06 3.4131: Minimize contamination of water before treatment $800 $1,548 - - $800 -
07 3.7391: Implement a maintenance program to keep racks and tanks free of rust, cracks, or corrosion $200 $2,040 - - $(-480.0) $680
TOTAL RECOMMENDED $70,463 $175,773 $22,467
438,991
kWh
$6,996
-
kW-mo/yr
$320 $40,680
TOTAL IMPLEMENTED $58,625 $169,625 $21,401
418,339
kWh
$7,024
-
kW-mo/yr
$(-480.0) $30,680
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs