ITAC Assessment: NL0075
ITAC logo
ITAC Assessment: NL0075
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Ham Products
NAICS 311612: Meat Processed from Carcasses
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 28,696
ft2
Annual Production 7,000,000
lb
Production Hrs. Annual 3,188
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,291 2,331,845
kWh
Electricity Demand $149,259 7,104
kW-mo/yr
Electricity Fees $11,422 -
Natural Gas $82,600 26,074
MMBtu
Waste Disposal Costs
Water Usage $30,216 8,470
Tgal
Water Disposal $40,190 8,470
Tgal
TOTAL YEARLY COSTS $368,978
RECOMMENDED SAVINGS* $25,869 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,479

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7229: Air condition only space necessary $13,412 $7,500 $13,412
570,709
kWh
- -
02 2.2437: Recover waste heat from equipment $7,755 $28,900 - - $7,755
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,087 $1,652 $718
29,934
kWh
$2,369
-
kW-mo/yr
-
04 2.2511: Insulate bare equipment $980 $404 $446
18,571
kWh
$535
-
kW-mo/yr
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $635 $575 $148
6,159
kWh
$487
-
kW-mo/yr
-
TOTAL RECOMMENDED $25,869 $39,031 $14,724
625,373
kWh
$3,391
-
kW-mo/yr
$7,755
-
MMBtu
TOTAL IMPLEMENTED $17,479 $9,556 $14,576
619,214
kWh
$2,904
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs