Assessment Year | 2022 |
---|---|
Principal Product | Treated Wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $1 M to 5M |
# of Employees | 11 |
Plant Area |
160,000
ft2
|
Annual Production | 1,118,100
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $182,657 | 4,684,533 |
kWh
|
$0.039 | |
Electricity Demand | $143,221 | 8,459 |
kW-mo/yr
|
$16.93 | |
Electricity Fees | $1,740 | - |
|
- | |
Natural Gas | $6,868 | 1,089 |
MMBtu
|
$6.31 | |
Waste Disposal Costs | |||||
Water Usage | $17,384 | 11,023 |
Tgal
|
$1.58 | |
TOTAL YEARLY COSTS | $351,870 | ||||
RECOMMENDED SAVINGS* | $88,573 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $88,573 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $44,258 | $7,000 |
$19,233
493,452
kWh
|
$25,025
-
kW-mo/yr
|
- | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $20,357 | $960 |
$20,357
521,968
kWh
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $17,011 | $25,884 |
$612
15,705
kWh
|
$1,595
-
kW-mo/yr
|
$14,804
-
Tgal
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,339 | $4,500 |
$3,348
85,848
kWh
|
$1,991
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,608 | $5,394 |
$398
10,208
kWh
|
$1,210
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $88,573 | $43,738 |
$43,948
1,127,181
kWh
|
$29,821
-
kW-mo/yr
|
$14,804
-
Tgal
|
||
TOTAL IMPLEMENTED | $88,573 | $43,738 |
$43,948
1,127,181
kWh
|
$29,821
-
kW-mo/yr
|
$14,804
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs