Assessment Year | 2019 |
---|---|
Principal Product | Treated Wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $500 k to 1M |
# of Employees | 27 |
Plant Area |
180,020
ft2
|
Annual Production | 142,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $367,474 | 7,044,800 |
kWh
|
$0.052 | |
Electricity Demand | $113,032 | 12,596 |
kW-mo/yr
|
$8.97 | |
Natural Gas | $42,119 | 9,912 |
MMBtu
|
$4.25 | |
Waste Disposal Costs | |||||
Water Usage | $375 | 355 |
Tgal
|
$1.06 | |
TOTAL YEARLY COSTS | $523,000 | ||||
RECOMMENDED SAVINGS* | $82,671 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4131: Size electric motors for peak operating efficiency | $59,550 | $111,550 |
$44,990
917,950
kWh
|
$14,560
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $21,092 | $690 |
$21,092
430,444
kWh
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,899 | $2,807 |
$1,387
28,295
kWh
|
$512
-
kW-mo/yr
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $130 | $46 |
$272
5,589
kWh
|
- | $(-92.0) | $(-50.0) | |
TOTAL RECOMMENDED | $82,671 | $115,093 |
$67,741
1,382,278
kWh
|
$15,072
-
kW-mo/yr
|
$(-92.0) | $(-50.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs