Assessment Year | 2017 |
---|---|
Principal Product | Ball and Roller Bearings, Precision Steel Balls |
NAICS | 332991: Ball and Roller Bearing Manufacturing |
SIC | 3562: Ball and Roller Bearings |
Sales Range | $100 M to 500M |
# of Employees | 435 |
Plant Area |
310,000
ft2
|
Annual Production | 55,000,000
units
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,899,653 | 39,320,047 |
kWh
|
$0.048 | |
Electricity Demand | $339,904 | 73,337 |
kW-mo/yr
|
$4.63 | |
Electricity Fees | $(-55,692.6) | - |
|
- | |
Natural Gas | $64,057 | 84,799 |
MMBtu
|
$0.76 | |
Waste Disposal Costs | |||||
Water Usage | $113,979 | 10,377 |
Tgal
|
$10.98 | |
Water Disposal | $51,933 | 10,377 |
Tgal
|
$5.00 | |
TOTAL YEARLY COSTS | $2,413,833 | ||||
RECOMMENDED SAVINGS* | $175,400 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $63,100 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $47,000 | $4,500 |
$47,000
1,008,000
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $44,400 | $160,000 |
$39,233
812,300
kWh
|
$5,167
-
kW-mo/yr
|
- | |
03 | 3.4116: Meter recycled water (to reduce sewer charges) | $33,100 | - | - | - | $33,100 | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $10,600 | $5,000 |
$8,461
175,300
kWh
|
$2,139
-
kW-mo/yr
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,800 | $1,000 |
$9,800
203,600
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,700 | $15,500 |
$16,311
336,600
kWh
|
$2,389
-
kW-mo/yr
|
- | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $9,600 | $90,000 | - |
$6,722
-
kW-mo/yr
|
$2,878 | |
08 | 3.4116: Meter recycled water (to reduce sewer charges) | $2,200 | - | - | - | $2,200 | |
TOTAL RECOMMENDED | $175,400 | $276,000 |
$120,805
2,535,800
kWh
|
$16,417
-
kW-mo/yr
|
$38,178 | ||
TOTAL IMPLEMENTED | $63,100 | $175,500 |
$55,544
1,148,900
kWh
|
$7,556
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs