ITAC Assessment: NL0011
ITAC logo
ITAC Assessment: NL0011
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Corrugated and Solid Fiber Box Manufacturing
NAICS 322211: Corrugated and Solid Fiber Box Manufacturing
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 53
Plant Area 230,000
ft2
Annual Production 200,000
thousand feet
Production Hrs. Annual 2,250
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $56,077 1,211,904
kWh
Electricity Demand $69,863 7,000
kW-mo/yr
Electricity Fees $6,141 -
Natural Gas $45,789 7,680
MMBtu
TOTAL YEARLY COSTS $177,870
RECOMMENDED SAVINGS* $13,738 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,729

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $6,874 - - $6,874
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,747 $20,139 $2,282
49,350
kWh
$2,465
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,135 $1,571 $1,579
34,118
kWh
- $(-444.0)
04 3.1291: Eliminate practice of mixing waste streams $982 - $982
21,356
kWh
- -
TOTAL RECOMMENDED $13,738 $21,710 $4,843
104,824
kWh
$9,339
-
kW-mo/yr
$(-444.0)
TOTAL IMPLEMENTED $5,729 $20,139 $3,264
70,706
kWh
$2,465
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs