ITAC Assessment: NL0007
ITAC logo
ITAC Assessment: NL0007
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Pork Products
NAICS 311612: Meat Processed from Carcasses
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $100
M
to 500
M
# of Employees 475
Plant Area 300,000
ft2
Annual Production 365,000,000
units
Production Hrs. Annual 3,600
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $588,274 22,988,750
kWh
Electricity Demand $888,155 43,938
kW-mo/yr
Electricity Fees $63,264 -
Natural Gas $696,000 161,000
MMBtu
Waste Disposal Costs
Water Usage $10,000 5,832
Tgal
TOTAL YEARLY COSTS $2,245,693
RECOMMENDED SAVINGS* $175,950 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $105,750

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Administrative Changes Savings
01 2.2437: Recover waste heat from equipment $62,200 $77,400 - - $62,200
-
MMBtu
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $47,300 $5,400 $49,000
1,930,000
kWh
- - - $(-1,700.0)
03 3.4156: Use flow control valves on equipment to optimize water use $36,200 $1,700 - - $26,200
-
MMBtu
$10,000
-
Tgal
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $16,300 $67,600 $7,448
291,700
kWh
$8,852
-
kW-mo/yr
- - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $8,000 $3,100 $3,294
126,600
kWh
$4,706
-
kW-mo/yr
- - -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,250 $12,000 $3,250
127,000
kWh
- - - -
07 2.2511: Insulate bare equipment $2,700 $840 - - $2,700
-
MMBtu
- -
TOTAL RECOMMENDED $175,950 $168,040 $62,992
2,475,300
kWh
$13,558
-
kW-mo/yr
$91,100
-
MMBtu
$10,000
-
Tgal
$(-1,700.0)
TOTAL IMPLEMENTED $105,750 $87,540 $59,698
2,348,700
kWh
$8,852
-
kW-mo/yr
$28,900
-
MMBtu
$10,000
-
Tgal
$(-1,700.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs