| Assessment Year | 2017 |
|---|---|
| Principal Product | Laboratory Analytical Instruments |
| NAICS | 334516: Analytical Laboratory Instrument Manufacturing |
| SIC | 3826: Laboratory Analytical Instruments |
| Sales Range | $50 M to 100M |
| # of Employees | 335 |
| Plant Area |
172,000
ft2
|
| Annual Production | 108,420
units
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $97,287 | 3,513,400 |
kWh
|
$0.028 |
| Electricity Demand | $210,494 | 11,145 |
kW-mo/yr
|
$18.89 |
| Electricity Fees | $14,892 | - |
|
- |
| Natural Gas | $62,336 | 7,260 |
MMBtu
|
$8.59 |
| TOTAL YEARLY COSTS | $385,009 | |||
| RECOMMENDED SAVINGS* | $56,745 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $56,745 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,351 | $69,750 |
$8,686
313,600
kWh
|
$14,215
-
kW-mo/yr
|
- | $2,450 | - | |
| 02 | 3.8142: Distill contaminated solvents for reuse | $14,999 | $22,000 |
$(-45.7)
(-1,650)
kWh
|
$(-680.0)
-
kW-mo/yr
|
$12,400
-
gal
|
- | $3,325 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,100 | - |
$11,100
401,868
kWh
|
- | - | - | - | |
| 04 | 2.3191: Use demand controller or load shedder | $4,082 | $4,000 |
$1,988
71,777
kWh
|
$2,094
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4235: Remove or close off unneeded compressed air lines | $1,213 | - |
$1,213
44,000
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $56,745 | $95,750 |
$22,941
829,595
kWh
|
$15,629
-
kW-mo/yr
|
$12,400
-
gal
|
$2,450 | $3,325 | ||
| TOTAL IMPLEMENTED | $56,745 | $95,750 |
$22,941
829,595
kWh
|
$15,629
-
kW-mo/yr
|
$12,400
-
gal
|
$2,450 | $3,325 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs