ITAC Assessment: NL0006
ITAC logo
ITAC Assessment: NL0006
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Laboratory Analytical Instruments
NAICS 334516: Analytical Laboratory Instrument Manufacturing
SIC 3826: Laboratory Analytical Instruments
Sales Range $50
M
to 100
M
# of Employees 335
Plant Area 172,000
ft2
Annual Production 108,420
units
Production Hrs. Annual 4,000
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $97,287 3,513,400
kWh
Electricity Demand $210,494 11,145
kW-mo/yr
Electricity Fees $14,892 -
Natural Gas $62,336 7,260
MMBtu
TOTAL YEARLY COSTS $385,009
RECOMMENDED SAVINGS* $56,745 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $56,745

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $25,351 $69,750 $8,686
313,600
kWh
$14,215
-
kW-mo/yr
- $2,450 -
02 3.8142: Distill contaminated solvents for reuse $14,999 $22,000 $(-45.7)
(-1,650)
kWh
$(-680.0)
-
kW-mo/yr
$12,400
-
gal
- $3,325
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $11,100 - $11,100
401,868
kWh
- - - -
04 2.3191: Use demand controller or load shedder $4,082 $4,000 $1,988
71,777
kWh
$2,094
-
kW-mo/yr
- - -
05 2.4235: Remove or close off unneeded compressed air lines $1,213 - $1,213
44,000
kWh
- - - -
TOTAL RECOMMENDED $56,745 $95,750 $22,941
829,595
kWh
$15,629
-
kW-mo/yr
$12,400
-
gal
$2,450 $3,325
TOTAL IMPLEMENTED $56,745 $95,750 $22,941
829,595
kWh
$15,629
-
kW-mo/yr
$12,400
-
gal
$2,450 $3,325
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs