| Assessment Year | 1997 |
|---|---|
| Principal Product | machined parts |
| NAICS |
n/a
|
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 109 |
| Plant Area |
30,000
ft2
|
| Annual Production | 110,000
units
|
| Production Hrs. Annual | 6,864
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $60,864 | 2,772,567 |
kWh
|
$0.022 |
| Electricity Demand | $43,604 | 5,898 |
kW-mo/yr
|
$7.39 |
| Natural Gas | $6,959 | 1,639 |
MMBtu
|
$4.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $570,741 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $2,292 | $3,164 | n/a |
$1,386
60,668
kWh
|
$906
-
kW-mo/yr
|
- | - | - |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,150 | $290 | n/a |
$670
30,481
kWh
|
$480
-
kW-mo/yr
|
- | - | - |
| 03 | 2.3212: Optimize plant power factor | $1,062 | $1,418 | n/a | - |
$1,062
-
kW-mo/yr
|
- | - | - |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $661 | $340 | n/a | - |
$661
-
kW-mo/yr
|
- | - | - |
| 05 | 2.7135: Install occupancy sensors | $546 | $400 | n/a |
$321
14,654
kWh
|
$225
-
kW-mo/yr
|
- | - | - |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $70 | $320 | n/a |
$41
1,758
kWh
|
$29
-
kW-mo/yr
|
- | - | - |
| 07 | 2.6218: Turn off equipment when not in use | $381 | $83 | n/a |
$381
10,258
kWh
|
- | - | - | - |
| 08 | 2.2437: Recover waste heat from equipment | $2,869 | $260 | n/a | - | - |
$2,869
-
MMBtu
|
- | - |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $830 | $280 | n/a |
$830
37,222
kWh
|
- | - | - | - |
| 10 | 4.652: Replace existing equipment with more suitable substitutes | $414,000 | $1,400,000 | n/a | - | - | - | - | $414,000 |
| 11 | 4.652: Replace existing equipment with more suitable substitutes | $103,520 | $240,000 | n/a | - | - | - | - | $103,520 |
| 12 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $27,360 | $12,500 | n/a | - | - | - |
$27,360
-
lb
|
- |
| 13 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $16,000 | $12,500 | n/a | - | - | - |
$16,000
-
lb
|
- |
| TOTAL RECOMMENDED | $570,741 | $1,671,555 |
$3,629
155,041
kWh
|
$3,363
-
kW-mo/yr
|
$2,869
-
MMBtu
|
$43,360
-
lb
|
$517,520 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs