| Assessment Year | 1996 |
|---|---|
| Principal Product | trucking equipment |
| NAICS |
n/a
|
| SIC | 3713: Truck and Bus Bodies |
| Sales Range | $5 M to 10M |
| # of Employees | 45 |
| Plant Area |
34,000
ft2
|
| Annual Production | 140
pieces
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $14,525 | 214,244 |
kWh
|
$0.068 |
| Natural Gas | $15,676 | 3,699 |
MMBtu
|
$4.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $2,381 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,381 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,445 | $500 |
$1,445
17,878
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $300 | $150 |
$300
3,810
kWh
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $300 | $175 |
$300
3,810
kWh
|
- | |
| 04 | 3.5316: Contract a wood pallet recycling company | $336 | - | - |
$336
-
lb
|
|
| TOTAL RECOMMENDED | $2,381 | $825 |
$2,045
25,498
kWh
|
$336
-
lb
|
||
| TOTAL IMPLEMENTED | $2,381 | $825 |
$2,045
25,498
kWh
|
$336
-
lb
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs