| Assessment Year | 2021 |
|---|---|
| Principal Product | Aircraft components |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
104,260
ft2
|
| Annual Production | 100,000
pieces
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $165,173 | 4,955,178 |
kWh
|
$0.033 | |
| Electricity Demand | $184,035 | 12,044 |
kW-mo/yr
|
$15.28 | |
| Electricity Fees | $55,160 | - |
|
- | |
| Natural Gas | $131,023 | 21,508 |
MMBtu
|
$6.09 | |
| Waste Disposal Costs | |||||
| Water Usage | $1 | 1 |
Tgal
|
$1.00 | |
| TOTAL YEARLY COSTS | $535,392 | ||||
| RECOMMENDED SAVINGS* | $33,471 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,041 | $11,374 |
$3,579
107,477
kWh
|
$4,462
-
kW-mo/yr
|
- | |
| 02 | 2.2437: Recover waste heat from equipment | $16,266 | $40,000 | - | - |
$16,266
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $854 | $300 |
$380
11,419
kWh
|
$474
-
kW-mo/yr
|
- | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $8,310 | $30,000 |
$3,818
114,660
kWh
|
$4,492
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $33,471 | $81,674 |
$7,777
233,556
kWh
|
$9,428
-
kW-mo/yr
|
$16,266
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs