| Assessment Year | 2021 |
|---|---|
| Principal Product | Dyed Goods |
| NAICS | 313310: Textile and Fabric Finishing Mills |
| SIC | 2262: Finishers of Broadwoven Fabrics of Manmade Fiber and Silk |
| Sales Range | $1 M to 5M |
| # of Employees | 80 |
| Plant Area |
150,000
ft2
|
| Annual Production | 3,000,000
lb
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $116,460 | 1,873,849 |
kWh
|
$0.062 | |
| Electricity Demand | $105,454 | 9,719 |
kW-mo/yr
|
$10.85 | |
| Natural Gas | $239,314 | 52,311 |
MMBtu
|
$4.57 | |
| Waste Disposal Costs | |||||
| Water Usage | $262,367 | 32,857 |
Tgal
|
$7.99 | |
| TOTAL YEARLY COSTS | $723,595 | ||||
| RECOMMENDED SAVINGS* | $127,788 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $8,055 | $3,000 | - | - |
$8,055
-
MMBtu
|
- | - | |
| 02 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $23,051 | $15,000 | - | - |
$26,051
-
MMBtu
|
- | $(-3,000.0) | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,619 | $5,000 |
$1,063
17,083
kWh
|
$556
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.4159: Replace treated water with well / surface water | $92,941 | $500 |
$(-928.0)
(-14,914)
kWh
|
$(-485.0)
-
kW-mo/yr
|
- |
$94,354
-
Tgal
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,952 | $4,258 |
$1,952
31,383
kWh
|
- | - | - | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $170 | $400 |
$170
2,730
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $127,788 | $28,158 |
$2,257
36,282
kWh
|
$71
-
kW-mo/yr
|
$34,106
-
MMBtu
|
$94,354
-
Tgal
|
$(-3,000.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs