| Assessment Year | 2020 |
|---|---|
| Principal Product | HVAC Equipment |
| NAICS | 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen |
| SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 208 |
| Plant Area |
280,000
ft2
|
| Annual Production | 40,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $106,016 | 1,663,840 |
kWh
|
$0.064 | |
| Electricity Demand | $89,835 | 8,330 |
kW-mo/yr
|
$10.78 | |
| Electricity Fees | $1,367 | - |
|
- | |
| Natural Gas | $79,995 | 11,759 |
MMBtu
|
$6.80 | |
| Waste Disposal Costs | |||||
| Water Usage | $1 | 1 |
Tgal
|
$1.00 | |
| TOTAL YEARLY COSTS | $277,214 | ||||
| RECOMMENDED SAVINGS* | $61,129 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $12,961 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $1,160 | $100 |
$1,160
18,202
kWh
|
- | - | - | |
| 02 | 2.7135: Install occupancy sensors | $631 | $700 |
$631
9,900
kWh
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $465 | $390 |
$231
3,623
kWh
|
$234
-
kW-mo/yr
|
- | - | |
| 04 | 2.8114: Change rate schedules or other changes in utility service | $11,865 | $500 |
$11,865
-
kWh
|
- | - | - | |
| 05 | 2.8114: Change rate schedules or other changes in utility service | $40,922 | $1,000 |
$(-49,944.0)
-
kWh
|
$89,835
-
kW-mo/yr
|
$1,031 | - | |
| 06 | 4.512: Condense operation into one building | $6,086 | $4,800 |
$1,159
18,200
kWh
|
$1,177
-
kW-mo/yr
|
- | $3,750 | |
| TOTAL RECOMMENDED | $61,129 | $7,490 |
$(-34,898.0)
49,925
kWh
|
$91,246
-
kW-mo/yr
|
$1,031 | $3,750 | ||
| TOTAL IMPLEMENTED | $12,961 | $1,590 |
$12,727
13,523
kWh
|
$234
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs