ITAC Assessment: NC0651
ITAC logo
ITAC Assessment: NC0651
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Upholstered furniture
NAICS 337121: Upholstered Household Furniture Manufacturing
SIC 2512: Wood Household Furniture, Upholstered
Sales Range $10
M
to 50
M
# of Employees 145
Plant Area 194,000
ft2
Annual Production 10,000
pieces
Production Hrs. Annual 2,100
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $81,163 1,525,900
kWh
Electricity Demand $58,840 6,310
kW-mo/yr
Natural Gas $38,794 5,124
MMBtu
Waste Disposal Costs
Water Usage $1 1
Tgal
TOTAL YEARLY COSTS $178,798
RECOMMENDED SAVINGS* $6,273 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,654

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,900 $12,818 $860
16,165
kWh
$1,040
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $754 $780 $341
6,414
kWh
$413
-
kW-mo/yr
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $949 $1,729 $430
8,075
kWh
$519
-
kW-mo/yr
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,407 $1,500 $637
11,979
kWh
$770
-
kW-mo/yr
-
05 2.2437: Recover waste heat from equipment $1,263 $5,000 - - $1,263
-
MMBtu
TOTAL RECOMMENDED $6,273 $21,827 $2,268
42,633
kWh
$2,742
-
kW-mo/yr
$1,263
-
MMBtu
TOTAL IMPLEMENTED $2,654 $13,598 $1,201
22,579
kWh
$1,453
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs