ITAC Assessment: NC0648
ITAC logo
ITAC Assessment: NC0648
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Sports apparel and uniforms
NAICS 315280: Other Cut and Sew Apparel Manufacturing
SIC 2329: Men's and Boys' Clothing, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 352,000
ft2
Annual Production 6,200,000
pieces
Production Hrs. Annual 5,400
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $274,362 4,624,332
kWh
Electricity Demand $107,456 10,867
kW-mo/yr
Natural Gas $32,684 5,668
MMBtu
Waste Disposal Costs
Water Usage $1 1
Tgal
TOTAL YEARLY COSTS $414,503
RECOMMENDED SAVINGS* $50,384 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $50,384

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $41,352 $169,512 $24,409
411,395
kWh
$16,943
-
kW-mo/yr
02 2.7135: Install occupancy sensors $7,874 $10,949 $7,874
132,717
kWh
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $251 $75 $183
3,093
kWh
$68
-
kW-mo/yr
04 2.2511: Insulate bare equipment $907 $1,200 $662
11,160
kWh
$245
-
kW-mo/yr
TOTAL RECOMMENDED $50,384 $181,736 $33,128
558,365
kWh
$17,256
-
kW-mo/yr
TOTAL IMPLEMENTED $50,384 $181,736 $33,128
558,365
kWh
$17,256
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs