| Assessment Year | 2020 |
|---|---|
| Principal Product | Wood chips and fuel for paper mills |
| NAICS | 321113: Sawmills |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $5 M to 10M |
| # of Employees | 8 |
| Plant Area |
3,300
ft2
|
| Annual Production | 260,000,000
lb
|
| Production Hrs. Annual | 2,625
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $32,943 | 420,480 |
kWh
|
$0.078 | |
| Electricity Demand | $13,509 | 3,453 |
kW-mo/yr
|
$3.91 | |
| Electricity Fees | $1,584 | - |
|
- | |
| Fuel Oil #2 | $55,485 | 3,515 |
MMBtu
|
$15.79 | |
| Waste Disposal Costs | |||||
| Water Usage | $4,646 | 454 |
Tgal
|
$10.23 | |
| Water Disposal | $5,866 | 454 |
Tgal
|
$12.92 | |
| TOTAL YEARLY COSTS | $114,033 | ||||
| RECOMMENDED SAVINGS* | $385,648 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $377,934 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings | Water Disposal Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $377,240 | $300,000 |
$(-18,620.0)
(-238,720)
kWh
|
$(-5,583.0)
-
kW-mo/yr
|
- |
$34,953
-
MMBtu
|
- | $366,490 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $225 | $778 |
$182
2,339
kWh
|
$43
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $188 | $83 |
$188
2,408
kWh
|
- | - | - | - | - | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $694 | $362 |
$1,638
21,000
kWh
|
$469
-
kW-mo/yr
|
- |
$(-1,413.0)
-
MMBtu
|
- | - | |
| 05 | 2.3212: Optimize plant power factor | $2,484 | $7,500 | - | - | $2,484 | - | - | - | |
| 06 | 3.4116: Meter recycled water (to reduce sewer charges) | $4,817 | $6,709 | - | - | - | - |
$4,817
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $385,648 | $315,432 |
$(-16,612.0)
(-212,973)
kWh
|
$(-5,071.0)
-
kW-mo/yr
|
$2,484 |
$33,540
-
MMBtu
|
$4,817
-
Tgal
|
$366,490 | ||
| TOTAL IMPLEMENTED | $377,934 | $300,362 |
$(-16,982.0)
(-217,720)
kWh
|
$(-5,114.0)
-
kW-mo/yr
|
- |
$33,540
-
MMBtu
|
- | $366,490 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings | Water Disposal Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs