Assessment Year | 2019 |
---|---|
Principal Product | Tools and display packs plus large distribution center |
NAICS | 333517: Machine Tool Manufacturing |
SIC | 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices |
Sales Range | $100 M to 500M |
# of Employees | 470 |
Plant Area |
500,000
ft2
|
Annual Production | 1,300,000
pieces
|
Production Hrs. Annual | 5,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $490,768 | 9,760,000 |
kWh
|
$0.050 |
Electricity Demand | $217,313 | 16,768 |
kW-mo/yr
|
$12.96 |
Natural Gas | $47,281 | 6,519 |
MMBtu
|
$7.25 |
TOTAL YEARLY COSTS | $755,362 | |||
RECOMMENDED SAVINGS* | $82,767 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $62,941 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4131: Size electric motors for peak operating efficiency | $28,909 | $65,575 |
$21,366
424,772
kWh
|
$7,543
-
kW-mo/yr
|
|
02 | 2.7232: Replace existing hvac unit with high efficiency model | $23,191 | $30,000 |
$11,661
231,831
kWh
|
$11,530
-
kW-mo/yr
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,841 | $25,826 |
$6,894
137,051
kWh
|
$3,947
-
kW-mo/yr
|
|
04 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,639 | - |
$1,639
32,585
kWh
|
- | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,800 | - | - |
$5,800
-
kW-mo/yr
|
|
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,387 | $50,000 |
$7,877
156,600
kWh
|
$4,510
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $82,767 | $171,401 |
$49,437
982,839
kWh
|
$33,330
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $62,941 | $121,401 |
$39,921
793,654
kWh
|
$23,020
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs