Assessment Year | 2019 |
---|---|
Principal Product | Water and wastewater |
NAICS | 221310: Water Supply and Irrigation Systems |
SIC | 4941: Water Supply |
Sales Range | $5 M to 10M |
# of Employees | 30 |
Plant Area |
14,500
ft2
|
Annual Production | 1,000,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $244,652 | 5,226,520 |
kWh
|
$0.047 |
Electricity Demand | $98,392 | 10,466 |
kW-mo/yr
|
$9.40 |
Electricity Fees | $1,704 | - |
|
- |
TOTAL YEARLY COSTS | $344,748 | |||
RECOMMENDED SAVINGS* | $51,259 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $30,092 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,832 | $700 | - |
$1,832
-
kW-mo/yr
|
|
02 | 2.8114: Change rate schedules or other changes in utility service | $30,092 | $500 |
$30,092
-
kWh
|
- | |
03 | 2.9114: Use solar heat to make electricty | $19,071 | $157,500 |
$7,779
175,200
kWh
|
$11,292
-
kW-mo/yr
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $264 | $1,283 |
$264
5,960
kWh
|
- | |
TOTAL RECOMMENDED | $51,259 | $159,983 |
$38,135
181,160
kWh
|
$13,124
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $30,092 | $500 |
$30,092
-
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs