ITAC Assessment: NC0640
ITAC logo
ITAC Assessment: NC0640
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Water and wastewater
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range $5
M
to 10
M
# of Employees 30
Plant Area 14,500
ft2
Annual Production 1,000,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $244,652 5,226,520
kWh
Electricity Demand $98,392 10,466
kW-mo/yr
Electricity Fees $1,704 -
TOTAL YEARLY COSTS $344,748
RECOMMENDED SAVINGS* $51,259 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,092

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,832 $700 - $1,832
-
kW-mo/yr
02 2.8114: Change rate schedules or other changes in utility service $30,092 $500 $30,092
-
kWh
-
03 2.9114: Use solar heat to make electricty $19,071 $157,500 $7,779
175,200
kWh
$11,292
-
kW-mo/yr
04 2.7142: Utilize higher efficiency lamps and/or ballasts $264 $1,283 $264
5,960
kWh
-
TOTAL RECOMMENDED $51,259 $159,983 $38,135
181,160
kWh
$13,124
-
kW-mo/yr
TOTAL IMPLEMENTED $30,092 $500 $30,092
-
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs