Assessment Year | 2019 |
---|---|
Principal Product | Cured meats and cut meats |
NAICS | 311612: Meat Processed from Carcasses |
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
350,000
ft2
|
Annual Production | 35,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $504,313 | 11,989,000 |
kWh
|
$0.042 | |
Electricity Demand | $391,290 | 23,127 |
kW-mo/yr
|
$16.92 | |
Electricity Fees | $(-80,372.0) | - |
|
- | |
LPG | $338,450 | 34,040 |
MMBtu
|
$9.94 | |
Waste Disposal Costs | |||||
Water Usage | $130,000 | 13,000 |
Tgal
|
$10.00 | |
TOTAL YEARLY COSTS | $1,283,681 | ||||
RECOMMENDED SAVINGS* | $194,382 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Water Usage Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,819 | $1,000 | - | - |
$1,819
-
MMBtu
|
- | - | |
02 | 2.2121: Increase amount of condensate returned | $4,196 | $8,200 | - | - |
$2,038
-
MMBtu
|
$1,439
-
Tgal
|
$719 | |
03 | 2.2437: Recover waste heat from equipment | $49,700 | $125,000 | - | - |
$49,700
-
MMBtu
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $18,727 | $25,000 |
$10,382
246,600
kWh
|
$8,345
-
kW-mo/yr
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,235 | $31,057 |
$10,011
237,800
kWh
|
$6,224
-
kW-mo/yr
|
- | - | - | |
06 | 2.8114: Change rate schedules or other changes in utility service | $103,705 | $500 |
$103,705
-
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $194,382 | $190,757 |
$124,098
484,400
kWh
|
$14,569
-
kW-mo/yr
|
$53,557
-
MMBtu
|
$1,439
-
Tgal
|
$719 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Water Usage Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs