Assessment Year | 2018 |
---|---|
Principal Product | Yarns |
NAICS | 313110: Fiber, Yarn, and Thread Mills |
SIC | 2284: Thread Mills |
Sales Range | $10 M to 50M |
# of Employees | 265 |
Plant Area |
285,000
ft2
|
Annual Production | 9,000,000
lb
|
Production Hrs. Annual | 7,800
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,468,314 | 38,020,000 |
kWh
|
$0.039 |
Electricity Demand | $730,912 | 75,002 |
kW-mo/yr
|
$9.75 |
Natural Gas | $12,720 | 1,632 |
MMBtu
|
$7.79 |
TOTAL YEARLY COSTS | $2,211,946 | |||
RECOMMENDED SAVINGS* | $204,282 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $204,282 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $49,355 | $165,749 |
$26,632
689,957
kWh
|
$11,829
-
kW-mo/yr
|
- | $10,894 | |
02 | 2.7135: Install occupancy sensors | $566 | $894 |
$566
14,653
kWh
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,681 | $200 |
$5,804
150,360
kWh
|
$2,077
-
kW-mo/yr
|
$(-100.0) | $(-100.0) | |
04 | 2.4239: Eliminate or reduce compressed air usage | $241 | $675 |
$241
6,255
kWh
|
- | - | - | |
05 | 2.4224: Upgrade controls on compressors | $7,353 | $15,000 |
$5,415
140,280
kWh
|
$1,938
-
kW-mo/yr
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,597 | $100 |
$6,330
164,000
kWh
|
$2,267
-
kW-mo/yr
|
- | - | |
07 | 2.7241: Install outside air damper / economizer on hvac unit | $100,563 | $75,000 |
$100,563
2,605,265
kWh
|
- | - | - | |
08 | 2.2623: Minimize condenser cooling water temperature | $29,926 | $2,000 |
$29,926
775,296
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $204,282 | $259,618 |
$175,477
4,546,066
kWh
|
$18,111
-
kW-mo/yr
|
$(-100.0) | $10,794 | ||
TOTAL IMPLEMENTED | $204,282 | $259,618 |
$175,477
4,546,066
kWh
|
$18,111
-
kW-mo/yr
|
$(-100.0) | $10,794 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs