| Assessment Year | 2017 |
|---|---|
| Principal Product | Chicken |
| NAICS | 311615: Poultry Processing |
| SIC | 2015: Poultry Slaughtering and Processing |
| Sales Range | $100 M to 500M |
| # of Employees | 720 |
| Plant Area |
125,000
ft2
|
| Annual Production | 2,400,000
lb
|
| Production Hrs. Annual | 6,600
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $560,166 | 12,955,000 |
kWh
|
$0.043 | |
| Electricity Demand | $286,580 | 25,152 |
kW-mo/yr
|
$11.39 | |
| Natural Gas | $281,263 | 67,293 |
MMBtu
|
$4.18 | |
| Waste Disposal Costs | |||||
| Water Usage | $780,804 | 223,247 |
Tgal
|
$3.50 | |
| TOTAL YEARLY COSTS | $1,908,813 | ||||
| RECOMMENDED SAVINGS* | $115,530 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $1,718 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,879 | $54,333 |
$12,710
294,204
kWh
|
$7,799
-
kW-mo/yr
|
- | - | $3,370 | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,718 | $100 |
$1,702
39,402
kWh
|
$816
-
kW-mo/yr
|
- | $(-400.0) | $(-400.0) | |
| 03 | 2.2437: Recover waste heat from equipment | $41,579 | $200,000 | - | - |
$41,579
-
MMBtu
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $30,012 | $39,000 |
$9,800
226,857
kWh
|
$4,647
-
kW-mo/yr
|
$15,565
-
MMBtu
|
- | - | |
| 05 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $18,342 | $85,000 |
$18,533
429,000
kWh
|
$8,884
-
kW-mo/yr
|
$(-9,075.0)
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $115,530 | $378,433 |
$42,745
989,463
kWh
|
$22,146
-
kW-mo/yr
|
$48,069
-
MMBtu
|
$(-400.0) | $2,970 | ||
| TOTAL IMPLEMENTED | $1,718 | $100 |
$1,702
39,402
kWh
|
$816
-
kW-mo/yr
|
- | $(-400.0) | $(-400.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs