ITAC Assessment: NC0596
ITAC logo
ITAC Assessment: NC0596
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Chicken
NAICS 311615: Poultry Processing
SIC 2015: Poultry Slaughtering and Processing
Sales Range $100
M
to 500
M
# of Employees 720
Plant Area 125,000
ft2
Annual Production 2,400,000
lb
Production Hrs. Annual 6,600
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $560,166 12,955,000
kWh
Electricity Demand $286,580 25,152
kW-mo/yr
Natural Gas $281,263 67,293
MMBtu
Waste Disposal Costs
Water Usage $780,804 223,247
Tgal
TOTAL YEARLY COSTS $1,908,813
RECOMMENDED SAVINGS* $115,530 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,718

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $23,879 $54,333 $12,710
294,204
kWh
$7,799
-
kW-mo/yr
- - $3,370
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,718 $100 $1,702
39,402
kWh
$816
-
kW-mo/yr
- $(-400.0) $(-400.0)
03 2.2437: Recover waste heat from equipment $41,579 $200,000 - - $41,579
-
MMBtu
- -
04 2.2437: Recover waste heat from equipment $30,012 $39,000 $9,800
226,857
kWh
$4,647
-
kW-mo/yr
$15,565
-
MMBtu
- -
05 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $18,342 $85,000 $18,533
429,000
kWh
$8,884
-
kW-mo/yr
$(-9,075.0)
-
MMBtu
- -
TOTAL RECOMMENDED $115,530 $378,433 $42,745
989,463
kWh
$22,146
-
kW-mo/yr
$48,069
-
MMBtu
$(-400.0) $2,970
TOTAL IMPLEMENTED $1,718 $100 $1,702
39,402
kWh
$816
-
kW-mo/yr
- $(-400.0) $(-400.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs