ITAC Assessment: NC0589
ITAC logo
ITAC Assessment: NC0589
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Urethane and rubber coated fabrics
NAICS 313320: Fabric Coating Mills
SIC 2295: Coated Fabrics, Not Rubberized
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area 250,000
ft2
Annual Production 12,000
thousand feet
Production Hrs. Annual 8,600
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $367,134 9,361,920
kWh
Electricity Demand $222,964 20,466
kW-mo/yr
Electricity Fees $811 -
Natural Gas $515,112 101,004
MMBtu
TOTAL YEARLY COSTS $1,106,021
RECOMMENDED SAVINGS* $129,451 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $35,979

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.2414: Use waste heat from hot flue gases to preheat $38,378 $62,575 - - $38,378
-
MMBtu
- - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,080 $19,100 $10,080
257,140
kWh
- - - - -
03 2.2444: Use hot process fluids to preheat incoming process fluids $4,455 $10,000 - - $4,455
-
MMBtu
- - -
04 4.424: Improve space comfort conditioning $28,966 $135,750 $(-6,139.0)
(-156,600)
kWh
$(-7,895.0)
-
kW-mo/yr
- - - $43,000
05 3.8142: Distill contaminated solvents for reuse $11,593 $10,750 $(-7,046.0)
(-179,740)
kWh
$(-2,861.0)
-
kW-mo/yr
- - $21,500 -
06 2.2136: Install / repair insulation on steam lines $3,876 $840 - - $3,876
-
MMBtu
- - -
07 2.1233: Analyze flue gas for proper air/fuel ratio $1,357 $1,000 - - $1,357
-
MMBtu
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $29,155 $66,186 $14,678
374,448
kWh
$7,031
-
kW-mo/yr
- - $7,446 -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $541 $300 $162
4,120
kWh
$64
-
kW-mo/yr
- - $315 -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,050 $100 $1,315
33,540
kWh
$535
-
kW-mo/yr
- $(-600.0) $(-200.0) -
TOTAL RECOMMENDED $129,451 $306,601 $13,050
332,908
kWh
$(-3,126.0)
-
kW-mo/yr
$48,066
-
MMBtu
$(-600.0) $29,061 $43,000
TOTAL IMPLEMENTED $35,979 $68,426 $16,155
412,108
kWh
$7,630
-
kW-mo/yr
$5,233
-
MMBtu
$(-600.0) $7,561 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs