ITAC Assessment: AR0183
ITAC logo
ITAC Assessment: AR0183
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Industrial Machinery
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 130,000
ft2
Annual Production 16,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $43,427 1,361,079
kWh
Electricity Demand $50,113 4,332
kW-mo/yr
Natural Gas $17,633 3,237
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $76,159 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $217

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Ancillary Material Cost Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,606 $4,020 $7,188
117,819
kWh
$3,418
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $672 $828 $448
586
kWh
$224
-
kW-mo/yr
- - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $217 - $144
2,345
kWh
$73
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,146 $4,224 $2,049
29,894
kWh
$1,097
-
kW-mo/yr
- - -
05 3.2123: Convert to high volume low pressure (hvlp) paint guns $20,376 $1,300 - - $15,647
-
Tgal
$4,729 -
06 4.452: Eliminate shift $41,142 - - - - - $41,142
TOTAL RECOMMENDED $76,159 $10,372 $9,829
150,644
kWh
$4,812
-
kW-mo/yr
$15,647
-
Tgal
$4,729 $41,142
TOTAL IMPLEMENTED $217 - $144
2,345
kWh
$73
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs